Operations & planning
Confirm SKU mix, order profile, peak windows, backlog tolerance and which exceptions are unacceptable during live fulfillment.
Evidence:Demand files, wave calendar, exception registerA warehouse control project crosses operations, IT/OT, maintenance, EHS and suppliers. Important assumptions, ownership boundaries and acceptance evidence should be visible early enough for the right people to challenge them.
Titles vary by project, but every control state, equipment handshake, safety action and test result needs an owner. The matrix identifies who provides input, who approves, who performs work and who receives the evidence.
Confirm SKU mix, order profile, peak windows, backlog tolerance and which exceptions are unacceptable during live fulfillment.
Evidence:Demand files, wave calendar, exception registerDefine rated conditions, operating envelope, guarding, maintenance access, controls behavior and documented limitations for installed assets.
Evidence:Submittal package, risk information, equipment test recordMap WMS, WCS, WES, PLC and fleet-management handshakes across normal, degraded and fault states with timeout and retry ownership.
Evidence:State diagram, I/O list, cause-and-effect reviewApprove isolation procedures, recovery access, training boundaries and restart authorization after an exception or cutover window.
Evidence:Operating procedure, training record, SAT observationFactory and site acceptance are not interchangeable. FAT can verify defined equipment and controls behavior before deployment, while SAT proves installation, interfaces and operating sequences in the real environment. The test basis should state preconditions, loads, roles, observations and how failed steps are closed.
Where a zone enters a live warehouse, commissioning also needs a traffic plan, fallback position and authority to stop. A phased release protects continuity only if operators know which modes are available during each window.
Freeze application assumptions, interface responsibilities and acceptance criteria before configuration decisions become expensive.
Exercise agreed sequences, alarms and recovery cases within the available factory or emulation boundary; record exclusions for site verification.
Verify geometry, power, network, devices, labels and guarded areas before energized operational testing.
Observe representative loads and traffic, close exceptions, deliver documentation and confirm who authorizes ongoing operation.
Application, integration and documentation support is defined by project scope. Equipment models, local regulations, service agreements, geography and site access determine the actual response path; they should not be replaced by a generic global coverage statement. Planning values such as a 1979 seed year, employee counts or country totals in configuration files are generated-range references and must not be published as verified corporate facts without source review.
Coordinate site dimensions, utilities, interfaces, access, delivery sequence and responsibilities.
Use approved test steps, representative conditions, issue tracking and signed handover evidence.
Connect diagnostics, critical spares, recovery procedures and escalation to the operating profile.